Honolulu rail CEO blames cost overruns on legal challenges, but critics say it is incompetence

16
10356
PROGRESS OR NOT? HART CEO Dan Grabauskas believes the city will prevail and the project will be built
article top
HART CEO Dan Grabauskas
HART CEO Dan Grabauskas

HONOLULU – Honolulu Area Rapid Transit director Daniel Grabauskas pledged on his watch, the city’s $5.26 billion Honolulu rail project would come in “on time and on budget.”

But as the Honolulu Star Advertiser notes, that’s not the case: “Construction of Honolulu’s rail transit system is on track to cost many millions of dollars more than originally thought. Rail officials this week opened the three bids they received to build the $5.26 billion project’s first nine stations. All three bids exceeded by well more than $100 million what they had originally budgeted for the work. The least expensive of the bids was still about 60 percent greater than what they had expected.”

inline

Grabauskas is apparently blaming the cost escalation on two legal challenges that halted the rail’s construction for just over a year.

As reported by the Star-Advertiser, Grabauskas told his HART’s board Thursday: “The time we lost because of those lawsuits … is what put us in this bid environment, and the market forces are what they are.”

The rail project was challenged twice in court.

The Native Hawaiian Legal Corporation and attorney David Frankel represented Paulette Kaleikini when she challenged the city’s decision to begin construction in the state’s highest court. She is a native Hawaiian with family members buried in Kakaako, possibly in the rail’s path. They won their case in August 2012, bringing the project to a halt for more than a year.

In a unanimous 82-page opinion in Kaleikini v. Yoshioka, Hawaii Supreme Court justices said the City did not comply with the State’s historic preservation and burial protection laws when it failed to complete an archeological inventory survey for the 20-mile route before starting construction. The court maintained: “it is undisputed that the rail project has a ‘high’ likelihood of having a potential effect on archeological resources….”

In a separate lawsuit, filed in 2011, eight plaintiffs including businessman Cliff Slater, former Gov. Benjamin Cayetano, retired Judge Walter Heen, University of Hawaii Law Professor Randal Roth, the Small Business Hawaii Education Foundation, Dr. Michael Uechi, Hawaii’s Thousand Friends and the Hawaii Outdoor Circle, challenged the city and FTA’s plans for the rail. The plaintiffs argued the project will bankrupt the city and destroy important cultural sites and the environment.

In their lawsuit, they maintained the city’s actions were “arbitrary” and “capricious” when:

  1. The city did not adequately consider viable transportation alternatives in its 2006 Alternatives Analysis before selecting heavy elevated steel on steel rail as the city’s mass transit system;
  2. The city did not vet alternatives in the Environmental Impact Statement, which may negatively impact Oahu’s historical sites and violated the National Environmental Policy Act;
  3. The city decided to conduct the archeological inventory in four phases, rather than surveying the entire 20-mile route before starting the project.

Slater, who heads HonoluluTraffic.com, disputed Grabauskas’ claim that legal challenges have increased the cost of the project.

“The delay was not caused by Honolulutraffic.com and its members. We had originally filed our lawsuit challenging the Final EIS in early 2011. Lawsuits in such cases cannot be filed until the Federal Transit Administration files its Record of Decision on the Final EIS so we could not have filed earlier. Our attorneys were well experienced in environmental law cases. In fact, our lead attorney wrote the regulations that implemented the National Environmental Policy Act (NEPA). At the time we filed the lawsuit our attorneys believed that it would all be resolved by the end of 2011. In the end, it was settled in 2014, over two years later,” Slater said.

“The City caused the delay by doing everything possible to impede a verdict; they believed that if they could get a sufficient portion of the rail line built before the verdict that the judges would allow that to influence their decision. I guess they were right. If you talk to our attorneys about the inordinate number of motions filed by the City, or review when we finally got the Administrative Record versus the time that it normally takes, you will see clearly that the City was fighting a delaying game the whole time,” Slater added.

“In addition, I do not believe that the City was ever precluded from putting the stations out to bid should they have wanted.”

Panos Prevedouros, PhD., a professor of engineering at the University, who has been a vocal opponent of the rail project, also dismissed Grabauskas’ claims.

“Anyway he cuts it, inflation is responsible for less than 10 percent of the 75 percent disparity,” Prevedouros said. “What should be startling is city’s and HARTs incompetence to price their project. Two of the three bidders offered to build it at double the cost the city budgeted.”

Comments

comments

bottom

16 COMMENTS

Comments are closed.